PMP Quiz 2


Points to remember
  • Choose 1 option out of 4 given options.
  • Mark yourself 1 point for every correct answer.
  • No negative marking for in-correct option chosen.
  • Answers are given at the end of questions.
  • Your Preparation stands good if you get anything over 75% of questions correct.
Disclaimer :- All Questions are taken from different public forums.if someone has copyright over any question material please reply with supporting information.that question will be removed.

1   your team finished creating the initial version of Risk Register During your Latest workshop. What is the Next thing you should do?
  A Define the probability of occurance and the impact of each risk
  B identify the risk effect and assign a numerical rating to each
  C review cost planning to ensure that enough risk reserve is available
  D identify analyse and plan for newly arisen risk
     
2   Pareto Diagram is used in which process
  A Plan Quality
  B Perform Quality Assurance
  C Perform quality control
  D Monitoring & Controling  
     
3   You are the project manager of a project in which you need to install a very sensitive machine. For some reason the machine is not working properly and your engineer believe that there may be Various factors ( Technical, enviornmental,Construction related etc.) involved in recuring breakdown.For your status report you would like to graphically display These possibily unrelated factors. what type of diagram illustrate this Best
  A Control chart
  B influence diagram
  C ishikawa diagram
  D Pareto chart
     
4   You are in charge of Canopy Water Scooter Company. You have recently launched
 a new water scooter and you observed some over-heating in the engine. You
 have decided to conduct a root cause analysis and to determine the exact
 reason for this and suggest action that could prevent the occurence of
 this in future models. Which of the following is true?
  A You are using the quality audit technique
  B You are using process analysis technique of QA
  C You are using Quality control tool and technique
  D You are using the root cause identification technique
     
5   A Chart that ranks causes of poor quality performance according to overall influence is called
  A A control chart
  B A cause and effect diagram
  C an ishikawa diagram
  D A Pareto diagram
     
6   You are the project manager for BC project. You need to find out which issue has maximum impact on the project. Which tool should you use?
  A pareto chart
  B control chart
  C trend analysis
  D fishbone diagram
     
7   A group of related schdule activites that for reporting purpose, is shown as a single aggregate activity
  A PDM
  B Combination activity
  C Roll-up activity
  D Hammock Activity
     
8   You are a project manager of a project and want to report the actual project result and the planned status. You should use?
  A Forcasting Report
  B Trend report
  C Status Report
  D Variance Report
     
9   You are the project manager on a project that has met all deliverables
 on schedule and on budget. What must be done to ensure all work was completed
 correctly and satisfactorily?
  A Perform product verification.
  B Obtain formal acceptance from the client.
  C Obtain formal approval from the contracts manager.
  D Perform a procurement audit.
     
10   You are working on internal projects for a big corporation. You are in
 to reqirement definition for new Claim system that will enable employees
 claim their hours worked on the projects using their mobile phones also.
 Due to budget cuts it was decided to cancel the project and deploy the
 people to commercial projects. Which of the following is true? 
  A The project ended due to integration because the resources where distributed
 to commercial projects
  B The project ended due to startvation because the funding was cut
  C The project ended due extinction because of the budget cut
  D The project ended due to integration because of budget cut
     
11   The outputs of the Close Project process include all the following except
 for which one?
  A Administrative closure procedure
  B Formal acceptance
  C Lessons learned
  D Closed contracts
     
12   According to Herzberg's theory of motivation , a base salary is
  A A primary motivator
  B A Secondary motivation
  C A hygine factor
  D Not a consideration in employee motivation
     
13   Herzberg identified factors, which, if present, will lead to increased motivation. A typical factor would be:
  A Good supervision
  B Job security
  C  Regular promotions
  D Good salary
     
14   This process assesses the priority of identified risks using their probability of occuring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project contstraints of cost schedule,scope and quality
  A Perform quality control
  B perform quantitative risk Analysis
  C perform qualitative risk analysis
  D perform quality management
     
15   Which of the following is true about pure risk?
  A The risk can be deflected or transferred to another party through a contract or insurance policy.
  B Pure risks involve the chance of both a profit and a loss.
  C No opportunities are associated with pure risk, only losses.
  D a and c
     
16   Which of the following models of conflict resolution allows a cooling off period, but seldom resolves the issue in the long term? 
  A A.Problem solving 
  B Withdrawal
  C Forcing
  D Smoothing
     
17   You are the project manager of a large software development project. There
 is a conflict between two module leads on where the changes have to be
 made. You intervene and tell them the importance of getting the project
 on time and ask them to find a solution which is acceptable to both of
 them. Which conflict resolution technique are you using here?
  A Confronting
  B Compromising
  C Smoothing
  D Forcing
     
18   In negotiating with functional department managers, project managers often find themselves using what two-party conflict management approach?
  A Win-Lose
  B Win-Win
  C Lose-Lose
  D None of the above
     
19   What conflict resolution technique is a project manager using when he says, "I cannot deal with this issue now!"
  A Problem solving
  B Forcing
  C Withdrawal
  D Compromising
     
20   A resolution that makes all parties unhappy is called _______.
  A Collaborative
  B Compromising
  C Strategic
  D All of the Above
     
    Answers
  1 D
  2 C
  3 C
  4 B
  5 D
  6 A
  7 D
  8 D
  9 B
  10 B
  11 D
  12 C
  13 C
  14 B
  15 D
  16 B
  17 C
  18 C
  19 C
  20 A